Latest NEWS


Gowrie at CLT Seal LTD
The Hengist Locomotive Project hosted their annual open day on Saturday, April 13 2024, at CTL Seal LTD in Sheffield showing the two...
4 days ago


Spring Update 2025
At the moment Stuart is concentrating on getting the trailing bogie to a suitable condition to go to the Hengist open day at CTL Seal on...
Mar 28


Winter Update 2024
We start this update with an image showing John Padget applying gloss paint to the inside of the carrier frames in readiness for the...
Dec 25, 2024


Tank Delivery
This was the day that the recently fabricated side tanks were delivered to the workshop to join the other components of the project. The...
Oct 18, 2024


Autumn Update 2024
In the last update, progress on the tanks and bunker had reached the stage where the left tank had been successfully water tested....
Sep 27, 2024


Bunker Update
We thought we would share some exciting news, that the bunker was delivered to the workshop on 3rd September and placed onto the frames...
Sep 4, 2024


Summer 2024 Update
As mentioned in the last update, instructions had been given for the second cylinder to be cast and since the patterns had been made for...
Jun 21, 2024


February 2024 Update
Since the last update further progress has been made on the bunker. The accompanying illustration shows the progress to the point where...
Feb 15, 2024


New Year 2024 Update
On the 28th December 2023 a small group attended the workshop. The main reason for this being to load the platework for the bunker, cab...
Jan 5, 2024


Winter 2023 Update
We have recently taken delivery of the leaf springs for the power bogie. Although these had been ordered at the same time as the trailing...
Dec 25, 2023


Summer 2023 Update
As on the previous update, the wheelsets for the trailing bogie were delivered to Statfold Engineering for the previously mentioned...
Sep 5, 2023


Spring 2023 Update
January 24th was a big day for the project. After months of work and a lot of planning it was a day of arrivals. Late morning the...
Apr 13, 2023


Winter 2022 Update
After the initial assembly of the power bogie frames, more work is needed before they are ready to be sent away to be riveted. There are...
Dec 21, 2022


November 2022 Update - Part 2
Following last weeks update we can now show you how much further the wheelsets have progressed. You can see that all the tyres have now...
Nov 21, 2022


November 2022 Update - Part 1
Following our appeal for match funding earlier this year, we were happy to report that we had received enough to cover the platework for...
Nov 10, 2022


Autumn 2022 Update
In the last update it was reported that some of the rivets had been delivered with the intention of fitting some of these once the...
Sep 28, 2022


Summer 2022 Update
Progress since the last update has been at a much slower pace for various reasons. It had been reported that the carrier frames were due...
Apr 30, 2022


Spring 2022 Update
In the last update we finished with the initial assembly of the carrier frames. As could be seen from the photographs it was easier to...
Mar 30, 2022


Autumn 2021 Update
Having assembled the rear bogie pivot stretcher for the carrier frames and the drilling of yet more holes. The time arrived to assemble...
Oct 13, 2021


Summer 2021 Update
Having received the frames and stretchers during December 2020, we hoped to make a start on drilling holes on the first Tuesday of 2021,...
Jun 22, 2021